Sign in
Under normal circumstances, it takes about 60 work days to accomplish a solar power project. However, the construction of this power plant must be completed and system has to be connected to grid within 43 business days, because the groundbreaking was near upon the end of November and according to regulation, the system connection to the network has to be completed by the end of the year. Despite the Taipower transmission and distribution line engineering that obstructs the construction progress, Hamak engineering team, being resolute to surmount all difficulties, has closely negotiated with TPC and finally, the system is successfully grid-connected at the end of the year.